Short answer

To assign a project task as a parent task in NetSuite, the prospective parent task must not have any estimated hours allocated to it. If a task has estimated time, it will not appear as an available option for selection as a parent. Ensure the parent task's estimated time field is empty to enable its use in structuring project hierarchies.

Scenario

Users attempting to structure project tasks in NetSuite may encounter situations where certain tasks are not available for selection as a parent task. This typically occurs when trying to establish a hierarchical relationship between tasks, but the desired parent task does not appear in the dropdown list of available options. This prevents the proper organization and nesting of project activities.

Solution

For a project task to be eligible for selection as a parent task, it must not have any estimated time assigned to it. If a task has estimated hours, NetSuite will not display it as an option when attempting to assign a parent task. To resolve this, navigate to the project task record and ensure the 'Estimated Work' or 'Estimated Time' field is empty. Once the estimated time is removed, the task will become available for selection as a parent task.

Expert NetSuite Support

Need help with this NetSuite issue?

Project Management consulting and configuration support

Talk to a consultant